The problem with Gantt charts in other tools
Most Gantt implementations show tasks as bars floating on a continuous date axis with no awareness of sprint boundaries. You end up with a flat timeline that does not reflect how your team actually works. Sprints are the unit of delivery for most engineering teams - the Gantt should honour that structure. Decuga's Timeline view is sprint-aware: each sprint occupies its own labeled band, tasks inside it are positioned relative to the sprint's start and end dates, and the overall date range is computed automatically from your sprint schedule. No manual date axis configuration.
How positioning works
A task bar's left edge is (startDate − sprintStart) / sprintDays × 100%. Its width is (dueDate − startDate) / sprintDays × 100%. Both are clamped to [0%, 100%] so tasks that span beyond the sprint still render within the band.
Reading the timeline
The left column shows sprint names. The scrollable right area is the Gantt canvas. Month labels run across the top so you always know which week you are looking at. A red vertical line marks today - tasks whose bars end before the red line are overdue. Tasks are color-coded by status: grey for To Do, blue for In Progress, green for Done. Hovering a bar shows the task title, assignee, and date range.
- ✓Sprint bands are shaded in a light indigo to visually separate them from the canvas background
- ✓Tasks assigned to the filtered assignee are highlighted; others are dimmed
- ✓Clicking any task bar opens the full task detail panel - same as clicking a card on the board
- ✓Unscheduled tasks (no startDate or dueDate) appear in a flat list below the Gantt area
Setting task start dates
Start dates are optional on every task. To add one, open the task detail panel (click any task on the board, backlog, or timeline). The Start Date badge sits to the left of the Due Date badge. Click it, pick a date from the calendar, and it saves immediately. The timeline updates on the next load. To clear a start date, click the badge again and select the clear option.
Bulk scheduling tip
Use the Backlog tab to assign due dates to all tasks in a sprint first, then set start dates in the task detail panels. Once start and due dates are set, the Timeline gives you an accurate picture of delivery schedule.
A sprint-aware timeline against a plain Gantt chart
The difference is easiest to see side by side. A plain Gantt chart treats the schedule as one long date axis, so a sprint boundary is just another day. A sprint-aware timeline treats the sprint as the unit of delivery: tasks sit inside the sprint they belong to, and the bar is drawn relative to that sprint's start and end. Questions that are awkward on a flat chart - what is in this sprint, does it fit, what slipped out of it - are visible at a glance.
Plain Gantt chart
- ×One continuous date axis
- ×No notion of a sprint boundary
- ×Tasks float without a delivery unit
- ×Dependencies are the focus
Sprint-aware timeline
- ✓Each sprint is its own band
- ✓Bars are positioned inside their sprint
- ✓Date range comes from the sprint schedule
- ✓Delivery pace is the focus
A worked example: reading a three-sprint timeline
Imagine a team with three sprints on the timeline and the following tasks. The example is illustrative, but the reading is what you would do on your own data. The first thing to look at is the red today line: any bar that ends to the left of it and is not green is overdue. Then look at how full each band is, and finally at the list of unscheduled tasks under the chart.
| What you see | What it usually means | What to do |
|---|---|---|
| A blue bar ends left of the today line | The task is overdue and still in progress | Ask the owner for a new date, or split the remaining work |
| One band is crowded with long overlapping bars | The sprint holds more parallel work than the team can finish | Move the lowest-priority tasks to the next sprint |
| A band has almost no bars | The next sprint is not planned yet | Pull ready tasks from the backlog and give them dates |
| A long list of unscheduled tasks | Tasks have no start or due date | Set dates for the ones that are in the sprint; leave backlog items unscheduled |
From a backlog to a schedule you can trust
A timeline is only as accurate as the dates behind it. The quickest route is to set the due dates first, because they are the commitments, and add start dates afterwards for the tasks where the duration matters. Then open the timeline, fix anything that looks wrong, and look again at the start of each week.
Getting an accurate timeline
- 1Due dates
Set them for every task in the sprint from the Backlog tab.
- 2Start dates
Add them in the task panel where duration matters.
- 3Open Timeline
Read it from the red today line outwards.
- 4Fix conflicts
Move, split or reassign the tasks that do not fit.
Look again at the start of each week, because dates drift
Timeline, board or burndown: which one to open
The three views answer different questions, and it helps to know which to open. The board is for today's work. The timeline is for the shape of the schedule. The burndown, covered in the visual project management guide, is for whether the sprint will finish on time.
| Question | Open | Why |
|---|---|---|
| What should I work on now? | The board | It shows status, one column at a time |
| Does the schedule fit the sprints? | The timeline | It shows bars inside each sprint band |
| Will this sprint finish on time? | The burndown | It compares remaining work with an even pace |
| Who has too much on? | The timeline, filtered by assignee, or the Workload view | Both show one person across tasks |
Available on all paid plans
Unlike Goals & OKRs (Pro and above), the Timeline view is available from the Starter plan upwards. No feature flags, no configuration - just navigate to the Timeline tab in any project. For teams on Free, the tab is hidden; upgrading to any paid plan unlocks it immediately.
- ✓Starter plan: $7/month flat - Timeline included
- ✓Pro plan: $28/month - adds Analytics, Retrospectives, Time Tracking
- ✓Business plan: $57/month - adds the service desk, SLA policies, change management
- ✓All plans: flat per-account pricing, no per-seat fees